A study puts a price on the wait to power AI data centers

Key Takeaways

  • modeling study compares grid, gas and two solar-storage designs, showing how deployment delays can change the lowest-cost source of power.
  • The authors compare four ways to power AI data centers in the continental United States.
  • Their model ranks options differently when it counts the computing capacity lost to delays.
  • A study of data center electricity asks whether an apparently cheap power supply still looks cheap if it delays when a computing facility can start.
  • The authors model four designs in the continental United States and assign a value to the computing work a facility could have done during the wait.

A study of data center electricity asks whether an apparently cheap power supply still looks cheap if it delays when a computing facility can start. The authors model four designs in the continental United States and assign a value to the computing work a facility could have done during the wait.

How the authors compare power options

The study evaluates grid interconnection, on-site natural gas and two solar-plus-storage designs, one coupled through alternating current and one using direct current. It models comparable energy service across the designs and accounts for cooling demand, power conversion and battery degradation. The authors use calibrated computing loads rather than treating the building as a constant electricity draw in every circumstance.

What changes when timing counts

The authors report that the direct-current design cut lifetime energy costs by 18% on average relative to the alternating-current equivalent in their model. Even so, the direct-current microgrids were rarely the lowest-cost option on the authors’ energy-only measure.
Adding the value of earlier computing changed the ranking. Under the main assumptions, the direct-current microgrid had the lowest modeled cost in 85% of the locations considered. The share fell to 55% under a scenario with faster natural gas deployment. Those are scenario results rather than observations of operating projects.

The assumptions worth checking

The result depends in part on when each system can realistically deliver power and on how much the operator values the computing capacity it gains by opening earlier. A site comparing options can ask for both estimates: the cost of the electricity delivered and the cost of waiting for it. That distinction is useful even at a site where the authors’ preferred design would rank differently.